Question: sub part 3. Please determine which job(s) being processed in time 15? 2. Use Johnson's rule to determine the optimal sequencing for the five jobs
sub part 3. Please determine which job(s) being processed in time 15?
2. Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times are given in the table below. Job Machine 1 Machine 2 w00 (1) What is the optimal sequence? (6 points) (2) What is the total flow time for this sequence? (8 points)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock