Question: Subject: Industrial Engineering For a summary work breakdown structure, at what level would a program schedule be prepared. O Level 1 Top-level O Level 2
Subject: Industrial Engineering

For a summary work breakdown structure, at what level would a program schedule be prepared. O Level 1 Top-level O Level 2 O Level 3 Question 11 The available scheduling methods include all the following EXCEPT: Gantt charts Program networks (PERT/CPM) Spreadsheet tracking O Bar charts Milestone charts