Question: SUBJECT: PROJECT MANAGEMET TOPIC: PROJECT COSTING AND EARNED VALUE MANAGMENT Requirements: Please calculate the cost of each ACTIVITY and the TOTAL COST of the Project.

SUBJECT: PROJECT MANAGEMET

TOPIC: PROJECT COSTING AND EARNED VALUE MANAGMENT

Requirements: Please calculate the cost of each ACTIVITY and the TOTAL COST of the Project. The duration and cost of each activity is given below the questions.

Q#01.

Calculate the cost of the following project:

Activity

Predecessor

Duration (Days)

Resources

A

-

5

PM

B

-

3

Analyst, PM

C

-

3

Engineer, Labor

D

A

4

Analyst, Engineer

E

B

4

PM, Engineer

F

C

3

Labor

G

D, E, F

2

Quality Manager

The payment rates of resources are as follows:

Resource

$/day

PM

$200

Analyst

$80

Engineer

$85

Quality Manager

$150

Labor

$50

Overhead Costs

$100

Q#02

Determine the total cost of the following project:

Activity

Duration

Predecessor

Resources

A

2

-

Worker 1, Crane

B

3

A

Worker 2, Bulldozer

C

3

A

Worker 3, Forklifter

D

5

C

Worker 1, Drill, Wiring (1000 Ft)

E

4

D

Worker 2, Paint (15 Liters)

Assume the following rates:

Resource

Rates

Worker 1

$50/hour

Worker2

$40/hour

Worker3

$45/hour

Crane

$500/day

Bulldozer

$1000/day

Forklifter

$300/day

Paint

$50/liter

Wiring

$15/ft

Drill

$60/day

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!