Question: SUBJECT:IDSC MAJOR: MIS From the reading: Why Projects Fail? Match three reasons project fail to the appropriate phase of the SDLC , justify with specific
SUBJECT:IDSC MAJOR: MIS
From the reading: "Why Projects Fail?" Match three reasons project fail to the appropriate phase of the SDLC , justify with specific deliverable and/or technique from the SDLC phase.
Refer to Figure 1-2 on page 9 of the text book. Feel free to state reasonable assumptions to address any ambiguity.
Example: Unmanaged risks are addressed by the risk assessment deliverable of the PLANNING phase of the SDLC.
choose 3 below this
1. Unrealistic or unarticulated project goals 2. Inaccurate estimates of needed resources 3. Badly defined system requirements 4. Poor reporting of the projects status 5. Unmanaged risks 6. Poor communication among customers, developers, and users 7. Use of immature technology 8. Inability to handle the projects complexity 9. Sloppy development practices 10. Poor project management 11. Stakeholder politics 12. Commercial pressures
TEXTBOOK:
| Phase | Chapter | Step | Technique | Deliverable |
| Planning | 1 | Identify opportunity | Project identification | System request |
| Focus: Why build this system? | 1 | Analyze feasibility | Technical feasibility Economic feasibility Organizational feasibility | Feasibility study |
| How to structure the project? | 2 | Develop workplan | Time estimation | Project plan |
| Primary outputs:
| Task identification Work breakdown structure PERT chart Gantt chart Scope management | Workplan | ||
| 2 | Staff project | Project staffing Project charter | Staffing plan | |
| 2 | Control and direct project | CASE repository Standards Documentation Timeboxing Risk management | Standards list Risk assessment | |
| Analysis | 3 | Develop analysis strategy | Business process automation | System proposal |
| Focus: Who, what, where, and when for this system? | 3 | Determine business requirements | Business process improvement Business process reengineering Interview | Requirements definition |
| Primary output | JAD session | |||
| System proposal | Questionnaire Document analysis Observation | |||
| 4 | Create use cases | Use case analysis | Use cases | |
| 5 | Model processes | Data flow diagramming | Process models | |
| 6 | Model data | Entity relationship modeling Normalization | Data model | |
| Design | 7 | Design physical system | Design strategy | Alternative matrix System specification |
| Focus: How will this system work? | 8 | Design architecture | Architecture design Hardware and software selection | Architecture report Hardware and software specification |
| Primary output:
| 9 | Design interface | Use scenario Interface structure Interface standards Interface prototype Interface evaluation | Interface design |
| 10 | Design programs | Data flow diagramming Program structure chart Program specification | Physical process model Program design | |
| 11 | Design databases and files | Data format selection Entity relationship modeling Denormalization Performance tuning Size estimation | Database and file specification Physical data model | |
| Implementation | 12 | Construct system | Programming | Test plan |
| Focus: Delivery and support of completed system | Software testing Performance testing | Programs Documentation | ||
| Primary output:
| 13 | Install system | Conversion strategy selection | Migration plan Conversion plan Business contingency plan |
| Training | Training plan | |||
| 13 | Maintain system | Support selection System maintenance Project assessment | Support plan Problem report Change request | |
| 13 | Postimplementation | Postimplementation audit | Postimplementation audit report |