Question: Success Systems second quarter 2010 fixed budget performance report for its computer furniture operations follows. The $156,000 budgeted expenses include $108,000 in variable expenses for
Success Systems second quarter 2010 fixed budget performance report for its computer furniture operations follows. The $156,000 budgeted expenses include $108,000 in variable expenses for desks and $18,000 in variable expenses for chairs, as well as $30,000 fixed expenses. The actual expenses include $31,000 fixed expenses. Prepare a flexible budget performance report that shows any variances between budgeted results and actual results. List fixed and variable expenses separately.

Explanation in excel would be greatly appreciated.