Question: Successful implementation of CCPM depends on first: Exploiting the drum by using it to subordinate the existing PERT network. Identifying the constraint that holds hostage

Successful implementation of CCPM depends on first:
Exploiting the drum by using it to subordinate the existing PERT network.
Identifying the constraint that holds hostage the project organization's other resources.
Identifying the critical chain that meanders through the project organization's portfolio of projects.
Examining and changing the culture of the project organization.
 Successful implementation of CCPM depends on first: Exploiting the drum by