Question: Sue Smith is developing a six - sigma quality certification program for managers. Smith has listed a number of activities that must be completed before

Sue Smith is developing a six-sigma quality certification program for managers. Smith has listed a number of activities that must be completed before a certification of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Predecessor Time (Days)
A -2
B -5
C -1
D C 10
E A,B 3
F D 6
G E,F 8
a. What is the critical path?
[ Select ]
b. What is the total project completion time?
[ Select ]
c. What is the slack time for each individual activity?
[ Select ]
d. What is the ES/EF and LS/LF for activity E?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!