Question: Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its
Sultan Company uses an activity-based costing system.
At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools:
| Activity Cost Pool | Activity Measure | Expected Overhead Cost | Expected Activity | ||||
| Labor-related | Direct labor-hours | $ | 390,600 | 43,400 | DLHs | ||
| Purchase orders | Number of orders | $ | 8,600 | 215 | orders | ||
| Parts management | Number of part types | $ | 94,160 | 107 | part types | ||
| Board etching | Number of boards | $ | 60,550 | 1,730 | boards | ||
| General factory | Machine-hours | $ | 220,800 | 18,400 | MHs | ||
Required:
1. Compute the activity rate for each of the activity cost pools.
2. The expected activity for the year was distributed among the companys four products as follows:
| Expected Activity | ||||||||||||
| Activity Cost Pool | Product A | Product B | Product C | Product D | ||||||||
| Labor-related (DLHs) | 5,800 | 28,400 | 4,800 | 4,400 | ||||||||
| Purchase orders (orders) | 71 | 20 | 43 | 81 | ||||||||
| Parts management (part types) | 28 | 20 | 42 | 17 | ||||||||
| Board etching (boards) | 310 | 770 | 650 | 0 | ||||||||
| General factory (MHs) | 2,500 | 6,400 | 4,000 | 5,500 | ||||||||
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock