Sun company makes special components for solar panel manufacturers. The cost details of job No: A007 is given below,
- The details material needed for job No: A007 is as follow,
Type of Material | Quantity needed | Cost per unit |
X | 750 cm | $20 per meter |
Y | 5 kg | $5 per kg |
- Royalty payment of $100 has to be paid to the designer of this solar panel for each unit they produce.
- The job needs a special machine which needs to be purchased for $500 and it has no residual value.
- This job needs to be completed in two departments and the details of those departments are given below,
Departments | Total Overhead | Machine Hours | Labour Hours |
Department A | $5000 | 500 | 1000 |
Department B | $8000 | 160 | 320 |
- Department A and Department B are labor-intensive and machine intensive respectively. Labors are paid a flat rate of $8 per hour regardless of the department they work.
- The job needs following labor and machine hours from each department.
Department | Labor hours | Machine hours |
Department A | 10 | 05 |
Department B | 05 | 10 |
- The company’s policy is to add 10% on prime cost for distribution cost and 10% of the total cost for administration expenses.
- The expected profit mark-up is 20% on the total cost.
You are required to:
Prepare an Operating Statement for the job, using the above information, showing clearly the Total Cost, Profit, and Selling Price.