Question: SUNY Empire State College MBA / PM Certificate Program Strategy and Tactics in Project Management Assignment 3 : Silver Zuma Project Part I The ARC
SUNY Empire State College
MBAPM Certificate Program
Strategy and Tactics in Project Management
Assignment : Silver Zuma Project Part I
The ARC Company specializes in developing and selling a wide range of highquality scooters. Sales representatives report that there is a growing demand for racing scooters. ARCs president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in XGame events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.
You are a member of a project team assigned to develop the new razor scooter code named Silver Zuma. Table contains the information necessary to create a project schedule. For the purpose of this case assume the following:
Unit A
The project begins January
The following holidays are observed: January Memorial Day last Monday in May July th Labor Day first Monday in September Thanksgiving Day th Thursday in November December and
If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.
The project team works eighthour days, Monday through Friday.
Table Silver Zuma Project
ID Task Name Duration Predecessors Resources
Product development project
Market analysis days Marketing Design
Product design days Marketing Design
Development Industrial
Manufacturing study days Industrial Development
Product design selection days Marketing Design
Development Industrial
Purchasing
Detailed marketing plans days Marketing
Manufacturing process days Design Development
Industrial
Detailed product design days Marketing Design
Development Industrial
Test prototype days Design Development
Finalized product design days Marketing Design
Development Industrial
Order components days Purchasing
Order production equipment days Purchasing
Install production equipment days FS days
FS days Development Industrial
Celebrate day Development Industrial Design Marketing Purchasing
Silver Zuma Project Page
Set up this project in MS Project and answer the following questions :
When is the project estimated to be completed date How long will the project take days
What is the critical path for the project? identify by task numbers
Which activity has the greatest amount of free slack?
Compare the advantagesdisadvantages of displaying the schedule as a network versus a Gantt chart.
Unit B
The following personnel have been assigned to the Silver Zuma project team:
Marketing Specialists
Design Engineers
Development Engineers
Industrial Engineers
Purchasing Agent
Table Silver Zuma Project Resources
Resource $hour Number Available
Marketing specialist $
Design engineer $
Development engineer $
Industrial engineer $
Purchasing agent $
Use the file from Unit A and the information contained in Tables and to assign resources to the project schedule. resources mean Answer the following questions:
What is the total cost of the Silver Zuma Project?
Which if any of the resources are over allocated?
Which activities involve over allocated resources?
Assume that the project is time constrained must be finished on time and try to resolve any over allocation problems by leveling within slack. Will this resolve overallocation?
Assume that the project is resource constrained and no additional personnel are available. How long will the project take given the resources assigned? Hint: Undo leveling performed in question before answering this question. Note: No splitting of activities is allowed.
How does the new duration compare with the estimated completion date generated from Unit A question What does this tell you about the impact of resources on project schedule?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock