Question: Super Good Corp. contracted to build a bridge for $ 5,000,000. Construction began in 2020 and was completed in 2021. Data relating to the construction

Super Good Corp. contracted to build a bridge for $ 5,000,000. Construction began in 2020 and was completed in 2021. Data relating to the construction are:

2020 2021

Costs incurred....................................................................... $ 1,620,000 $ 1,400,000

Estimated costs to complete................................................... 1,380,000

Instructions

Using the percentage-of-completion method and the cost-to-cost basis

How much revenue should be reported for 2020? Show your calculation.

Prepare the journal entry to record progress billings of $ 1,700,000 during 2020.

Prepare the journal entry to record the revenue and gross profit for 2020.

How much gross profit should be reported for 2021? Show your calculation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!