Question: SuperValue Distribution Center has 1 4 night - shift employees and 1 3 trucks to be loaded before 3 : 0 0 am . The

SuperValue Distribution Center has 14 night-shift employees and 13 trucks to be loaded before 3:00 am. The time (number of minutes) required to load each truck by employees is shown in Question 25 Data.xlsx.
SuperValue wants to minimize the total loading time needed to complete all loading jobs, given that
-All trucks must be loaded
-All employees must be assigned to at least one loading job
-Truck #2 must be loaded by Employee #6
-Employee #4 must not be loading Truck #1
-Two employees must be loading Truck #13 assume that, for Truck #13, loading times are already adjusted for a two-employee loading requirement
-Truck #3 must be loaded by either Employee #3 or Employee #9
Question #25 Based on the information provided, what is the minimum total loading time required to complete all loading jobs? Round your answer to two decimal places (e.g.,1,234.56 minutes).
Based on the information provided, the minimum total loading time required to complete all loading jobs is ____________________ minutes. Use the following narrative for Question 25
SuperValue Distribution Center has 14 night-shift employees and 13 trucks to be loaded before 3:00 am. The time (number of minutes) required to load each truck by employees is shown in "Question 25 Data.xlsx".
SuperValue wants to minimize the total loading time needed to complete all loading jobs, given that
- All trucks must be loaded
- All employees must be assigned to at least one loading job
- Truck \#2 must be loaded by Employee \#6
- Employee \#4 must not be loading Truck \#1
- Two employees must be loading Truck \#13- assume that, for Truck \#13, loading times are already adjusted for a two-employee loading requirement
- Truck \#3 must be loaded by either Employee \#3 or Employee \#9
Question \#25 Based on the information provided, what is the minimum total loading time required to complete all loading jobs? Round your answer to two decimal places (e.g.,1,234.56 minutes).
Based on the information provided, the minimum total loading time required to complete all loading jobs is minutes.
 SuperValue Distribution Center has 14 night-shift employees and 13 trucks to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!