Question: Suppose a sprint backlog includes 4 user stories at the beginning of a sprint: User Story A ( 5 points ) User Story B (
Suppose a sprint backlog includes user stories at the beginning of a sprint:
User Story A points
User Story B point
User Story C points
User Story D points
Now suppose that at the end of the sprint, User Story D has not been started, User Story C is in progress, and User Stories A and B have been completed. What was the team's velocity for this sprint?
points
points
points
points