Question: Suppose an operations manager made the following partially complete aggregate plan. September October November December Beg. Inventory 50 0 Reg. Time Production 1,000 1,000 1,000

Suppose an operations manager made the following partially complete aggregate plan.

September

October

November

December

Beg. Inventory

50

0

Reg. Time Production

1,000

1,000

1,000

1,000

Overtime Production

500

500

0

Subcontracting

0

100

0

100

Sales

1,600

1,575

900

1,300

Ending inventory

0

0

Back orders

25

0

Average inventory

0

Compute the blank entries in the plan and answer the following questions.

  1. What is the overtime production for December?

A. 125

B. 200

C. 300

D. 375

E. 450

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!