Question: Suppose for a particular process that the bottleneck cycle time is 54 seconds, and raw processing time is 345 seconds. If there are 9 customers
Suppose for a particular process that the bottleneck cycle time is 54 seconds, and raw processing time is 345 seconds. If there are 9 customers in this system already, and then you walk up and join the line at Station 1, what is your expected lead-time to move through the entire process? Whole number value, no decimals.