Question: Suppose operation X feeds directly into operation Y . All of X ' s output goes to Y , and Y has no other operations

Suppose operation X feeds directly into operation Y. All of X's output goes to Y, and Y has no other operations feeding into it. X has a design capacity of 80 units per hour and an effective capacity of 72 units per hour. Y has a design capacity of 100 units per hour. What is Y's maximum possible utilization?A.72 percentB.80 percentC.60 percentD.70 employeesE.90 percent