Question: Suppose that a summary activity, according to a project plan, would take 4 weeks and cost a total $40,000.00. Assume that 20% of the total
Suppose that a summary activity, according to a project plan, would take 4 weeks and cost a total $40,000.00. Assume that 20% of the total costs has been spent in the first week. The actual cost for the week is: Select one: a. $20,000.00 b. $10,000.00 $40,000.00 d. $8,000.00