Question: Suppose that B, E, and G form a critical path for a project and the activity variances are 4, 36, and 25 respectively. a. The

Suppose that B, E, and G form a critical path for
Suppose that B, E, and G form a critical path for a project and the activity variances are 4, 36, and 25 respectively. a. The overall project variance, opis (enter a numerical value). b. To the nearest tenth, the overall project standard deviation equals (enter a numerical value). c. The standard deviation for activity B is (enter a numerical value). d. The standard deviation for activity E is (enter a numerical value). e. The standard deviation for activity G is (enter a numerical value). f. The sum of the activity standard deviations in this critical path is (enter a numerical value). 8 Can one add activity standard deviations to calculate the project standard deviation? (enter a numerical value: 1-yes, O=no)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!