Question: Suppose that resources ( i . e . team members ) are generic, i . e . each resource can work on each task, but
Suppose that resources ie team members are generic, ie each resource can work on each task, but the different tasks require a different amount of resources, as shown in the following table:
WorkBreakdownStructure and Task Duration Estimates with Generic Resources
Task Predecessor Duration days # of Resources
A
B A
C A
D B
E B
F C
G D
H EF
I GH
Your boss asks you how many resources she should assign to support the project, ie :
What would be the optimal minimum amount of resources you need to have available on any day during the project that would allow you to complete the project without delays and how long will it take?