Question: Suppose that resources ( i . e . team members ) are generic, i . e . each resource can work on each task, but

Suppose that resources (i.e. team members) are generic, i.e. each resource can work on each task, but the different tasks require a different amount of resources, as shown in the following table:
Work-Breakdown-Structure and Task Duration Estimates with Generic Resources
Task Predecessor Duration (days) # of Resources
A -25
B A 43
C A 32
D B 26
E B 54
F C 44
G D 43
H E,F 63
I G,H 22
Your boss asks you how many resources she should assign to support the project, i.e. :
What would be the optimal minimum amount of resources you need to have available on any day during the project that would allow you to complete the project without delays and how long will it take?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!