Question: Suppose that the normal time for activity C is 10 weeks with a normal cost of $6,000. We can crash it to only 4 weeks
Suppose that the normal time for activity C is 10 weeks with a normal cost of $6,000. We can crash it to only 4 weeks at a total cost of $12,000. The total activity cost if we crash it to 7 weeks will be
A). $11,000.
B). $9,000.
C). $6,000.
D). $8,000.
Step by Step Solution
3.47 Rating (157 Votes )
There are 3 Steps involved in it
Given Normal time for activity 10 weeks Normal cost ... View full answer