Question: Suppose that you have the two projects as below: Project B Project A Year 200 1,000 1 600 800 2 800 600 3 1,200 200
Suppose that you have the two projects as below:
| Project B | Project A | Year |
| 200 | 1,000 | 1 |
| 600 | 800 | 2 |
| 800 | 600 | 3 |
| 1,200 | 200 | 4 |
Each project has a cost of $ 2,000 and the total cost of capital is 10%.
Determine which project should be accepted ?Using Net present value (NPV)