Question: Suppose the cash flows for two projects (A and B) are given as below. Both projects last for 3 years Present_Worth (A)=$23,397. Present_Worth (A)=$25,565. Present_Worth


Suppose the cash flows for two projects (A and B) are given as below. Both projects last for 3 years Present_Worth (A)=$23,397. Present_Worth (A)=$25,565. Present_Worth (A)=$28,855. Present_Worth (A)=$24,345. Present_Worth(B) =$20,397. Present_Worth (B)=$17,191. Present_Worth (B)=$14,083. Present_Worth (B)=$23,191. Based on the PW, Project A should be selected. Banew he PW, Project B should be selected