Question: Suppose the times for the individual operations for the in-line skate assembly are as follows: Task Description Time (sec) 1 Assemble wheels, bearings, and axle

Suppose the times for the individual operations for the in-line skate assembly are as follows:

Task

Description

Time (sec)

1

Assemble wheels, bearings, and axle hardware

11

2

Assemble brake housing and pad

7

3

Complete wheel assembly

18

4

Inspect wheel assembly

10

5

Assemble boot

16

6

Join boot and wheel subassemblies

8

7

Add line and final assembly

7

8

Perform final inspection

11

Consider the production line achieving an output rate of 200 per hour below. Using the proposed design, calculate the total time and idle time for each workstation. If your answer is zero, enter "0". Round your answers to the nearest whole number.

Station

Tasks

Total Time, seconds

Idle Time, seconds

A

1 and 2

B

3

C

5

D

4 and 6

E

7 and 8

Total

What is the assembly line efficiency? Round your answer to one decimal place.

%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!