Question: Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay $40 per day for a temporary
Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-cost project schedule using below format.
The AON diagram for the community center project is below.
.
Fill in the blanks
|
| Normal | Crash | Maximum | Crashing cost | |||
| Activity | Time (days) | Cost ($) | Time (days) | Cost ($) | Reduction | $ per Day | |
| START | 0 | 0 | 0 | 0 | ------ | ------- | |
| A | 10 | 50 | 8 | 150 |
|
| |
| B | 4 | 40 | 2 | 200 |
|
| |
| C | 7 | 70 | 6 | 160 |
|
| |
| D | 2 | 20 | 1 | 50 |
|
| |
| E | 3 | 30 | NONE | NONE |
|
| |
| F | 8 | 80 | 5 | 290 |
|
| |
| G | 5 | 50 | 4 | 180 |
|
| |
| H | 6 | 60 | 3 | 180 |
|
| |
| FINISH | 0 | 0 | 0 | 0 | ------ | ------ | |
The critical path is at .. days.