Question: Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay $40 per day for a temporary

Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-cost project schedule using below format.

The AON diagram for the community center project is below.

.

Fill in the blanks

Normal

Crash

Maximum

Crashing cost

Activity

Time (days)

Cost ($)

Time (days)

Cost ($)

Reduction

$ per Day

START

0

0

0

0

------

-------

A

10

50

8

150

B

4

40

2

200

C

7

70

6

160

D

2

20

1

50

E

3

30

NONE

NONE

F

8

80

5

290

G

5

50

4

180

H

6

60

3

180

FINISH

0

0

0

0

------

------

The critical path is at .. days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!