Question: Suppose the work on a project task was expected to cost 1 5 0 0 , to complete the task and the workers were

Suppose the work on a project task was

expected to cost 1500, to complete the task

and the workers were originally scheduled to

finish early.

As of today however, the workers have

expended 1350, and the best estimate is

that they are about 2/3 finished.

Calculate the

 Cost Variance

 Schedule variance

 Cost Performance Index

 Schedule Performance Index

Comment on this project

 

Step by Step Solution

3.51 Rating (154 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer To calculate the metrics requested well use the following formulas 1 Cost Variance CV Earned ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!