Question: Suppose the work on a project task was expected to cost 1 5 0 0 , to complete the task and the workers were
Suppose the work on a project task was
expected to cost to complete the task
and the workers were originally scheduled to
finish early.
As of today however, the workers have
expended and the best estimate is
that they are about finished.
Calculate the
Cost Variance
Schedule variance
Cost Performance Index
Schedule Performance Index
Comment on this project
Step by Step Solution
3.51 Rating (154 Votes )
There are 3 Steps involved in it
Answer To calculate the metrics requested well use the following formulas 1 Cost Variance CV Earned ... View full answer