You are the Project Engineer for a school project which is experiencing water leak issues. The...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
You are the Project Engineer for a school project which is experiencing water leak issues. The project is a three-story classroom building (steel stud, drywall, and stucco finish) and a single-story auditorium building (masonry). Both buildings were built seven years ago. The school authorities are complaining that they are experiencing water leaks in both buildings and in most of the rooms during the rainy season. They suspect the water is coming from the windows and from the ceiling/roof on the 3rd floor. Be advised that the school authorities have also made it clear that this work can only be done during the summer break as they cannot disrupt any classes during construction - this gives you 70 calendar days to complete the project. Please provide an explanation on how you will resolve these issues. In your response, please be sure to address the following: Identify the scope of the project What will be your main focus while preparing the contract documents? What kind of contract procurement method (JOC, Formal Bid. 17406, etc.) would you recommend for this type of project and why? Explain how you will ensure that this work can be achieved in the short time of 70 calendar days. You are the Project Engineer for a school project which is experiencing water leak issues. The project is a three-story classroom building (steel stud, drywall, and stucco finish) and a single-story auditorium building (masonry). Both buildings were built seven years ago. The school authorities are complaining that they are experiencing water leaks in both buildings and in most of the rooms during the rainy season. They suspect the water is coming from the windows and from the ceiling/roof on the 3rd floor. Be advised that the school authorities have also made it clear that this work can only be done during the summer break as they cannot disrupt any classes during construction - this gives you 70 calendar days to complete the project. Please provide an explanation on how you will resolve these issues. In your response, please be sure to address the following: You are the Project Engineer for a school project which is experiencing water leak issues. The project is a three-story classroom building (steel stud, drywall, and stucco finish) and a single-story auditorium building (masonry). Both buildings were built seven years ago. The school authorities are complaining that they are experiencing water leaks in both buildings and in most of the rooms during the rainy season. They suspect the water is coming from the windows and from the ceiling/roof on the 3rd floor. Be advised that the school authorities have also made it clear that this work can only be done during the summer break as they cannot disrupt any classes during construction - this gives you 70 calendar days to complete the project. Please provide an explanation on how you will resolve these issues. In your response, please be sure to address the following: You are the Project Engineer for a school project which is experiencing water leak issues. The project is a three-story classroom building (steel stud, drywall, and stucco finish) and a single-story auditorium building (masonry). Both buildings were built seven years ago. The school authorities are complaining that they are experiencing water leaks in both buildings and in most of the rooms during the rainy season. They suspect the water is coming from the windows and from the ceiling/roof on the 3rd floor. Be advised that the school authorities have also made it clear that this work can only be done during the summer break as they cannot disrupt any classes during construction - this gives you 70 calendar days to complete the project. Please provide an explanation on how you will resolve these issues. In your response, please be sure to address the following: Identify the scope of the project What will be your main focus while preparing the contract documents? What kind of contract procurement method (JOC, Formal Bid. 17406, etc.) would you recommend for this type of project and why? Explain how you will ensure that this work can be achieved in the short time of 70 calendar days. Identify the scope of the project What will be your main focus while preparing the contract documents? What kind of contract procurement method (JOC, Formal Bid. 17406, etc.) would you recommend for this type of project and why? Explain how you will ensure that this work can be achieved in the short time of 70 calendar days. Identify the scope of the project What will be your main focus while preparing the contract documents? What kind of contract procurement method (JOC, Formal Bid. 17406, etc.) would you recommend for this type of project and why? Explain how you will ensure that this work can be achieved in the short time of 70 calendar days.
Expert Answer:
Related Book For
Microeconomics An Intuitive Approach with Calculus
ISBN: 978-0538453257
1st edition
Authors: Thomas Nechyba
Posted Date:
Students also viewed these accounting questions
-
A certain bridge arch is in the shape of half an ellipse 120 feet wide and 30.7 feet high. At what horizontal distance from the center of the arch is the height equal to 16.9 feet? feet 1 answer
-
A 14-foot piece of string is cut into two pieces so that the longer piece is 2 feet longer than twice the shorter piece. Find the lengths of both pieces. What is the lenath of the shorter oiece?1...
-
suppose there is a 1.2 drop in temperature for every thousand feet that an airplane climbs into the sky. if the temperatureon the ground is 63.1, what will be the temperature when the plane reaches...
-
Direct Materials Budget The MSC Company has anticipated its unit sales for the first half of 2022 as follows: 2022 Units January 12,000 February 14,000 March 15,000 16,000 17,000 18,000 April May...
-
Clear Sound Audio uses a periodic inventory system. One of the store's most popular products is an MP8 car stereo system. The inventory quantities, purchases, and sales of this product for the most...
-
Packaging Solutions Corporation manufactures and sells a wide variety of packaging products. Performance reports are prepared monthly for each department. The planning budget and flexible budget for...
-
Why is it necessary to sometimes redact portions of a document that is produced to the opposing side?
-
Diderot Corp. acquired a property on September 15, 2014, for $220,000, paying $3,000 in transfer taxes and a $1,500 real estate fee. Based on the provincial assessment information, 75% of the...
-
Cowboy Recording Studio is considering the investment of $138,600 in a new recording equipment. It is estimated that the new equipment will generate additional cash flow of $20,500 per year for each...
-
The records of the Liwanag Refrigerator Company show the following information for the three months ended March 31, 19A: Materials Purchased P1,946,700 Inventories, Jan 1, 19A: Materials Finished...
-
Q1) If we are using a 200 line per mm diffraction grating, what is the value of the parameter a in units of microns? Q2) If we are observing the m=1 spectrum at a wavelength of 0.6 micron with the...
-
The costs per equivalent unit of direct materials and conversion in the Rolling Department of Jabari Steel Company are $1.30 and $1.85, respectively. The equivalent units to be assigned costs are as...
-
1. What have been some of the economic impacts of the war in Ukraine on theRussian economy? (Discuss at least 2 different impacts) 2. Discuss two reasons why global food shortages may occur as a...
-
A person inherited $34000 and invests it immediately at 8.75% compounded monthly. The person decides to quit his/her job and withdraws $1700 at the end of each month for as long as possible. a. How...
-
A bond is selling at par with the Macaulay duration of 11.2 years and the modified duration of 10.6 years. The convexity of the bond is 196. According to the duration rule, a 2% decrease in yield...
-
Let F = (5t + 4) i + sin(4t) j + e k Find F' (t), F" (t) and F""(t) (1) F' (t) = (2) F"(t) = = (3) F"" (t) = =
-
Explain the term global capital markets. This chapter primarily discusses global equity markets. What other types of financial instruments are traded in these markets? How important are global...
-
We discussed in the text the basic externality problem that we face when we rely on private giving to public projects. In this exercise, we consider how this changes as the number of people involved...
-
A: Suppose you have a homothetic production technology and you face output price p and input prices ( w , r ) . (a) On a graph with labor on the horizontal and capital k on the vertical axis, draw an...
-
The following is intended to explore what kinds of own-price demand relationships are logically possible in a two-good model with exogenous income (unless otherwise specified). A: For each of the...
-
Following is a probability density curve with the area between 0 and 1 and the area between 1 and 2 indicated. a. What proportion of the population is between 0 and 1? b. What is the probability that...
-
Use Table A.2 to find the area between z = 1.13 and z = 2.02. Z 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 -0.8 -0.7 .2119 .2090 .2420 2389 -0.6 .2743 .2709 .2676 .2061 .2033 2358 .2327 .2643...
-
Use Table A.2 to find the area to the left of z = 0.25. Z 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 -0.8 -0.7 .2119 .2090 .2420 2389 -0.6 .2743 .2709 .2676 .2061 .2033 2358 .2327 .2643 .2005...
Study smarter with the SolutionInn App