Question: Suppose we are formulating a Master Production Schedule (MPS) for an item. The lot-size policy for this item calls for a fixed quantity of 400
Suppose we are formulating a Master Production Schedule (MPS) for an item. The lot-size policy for this item calls for a fixed quantity of 400 units. Lead time for this item is three weeks. Week 0 inventory for this item is 400 units. There are no safety stock requirements.
Here are the demand forecast and the booked orders for this item ...
| Week | ||||||
| 1 | 2 | 3 | 4 | 5 | 6 | |
| Forecast | 120 | 120 | 100 | 100 | 100 | 120 |
| Booked | 130 | 128 | 76 | 0 | 0 | 0 |
When the master schedule is complete, what will be the Projected On-Hand in Week 4?