Question: Suppose you are evaluating a project using the net present value (NPV) method. You note that when you use the project cost of capital, the
Suppose you are evaluating a project using the net present value (NPV) method. You note that when you use the project cost of capital, the project NPV is negative. When you use the company cost of capital, the project NPV is positive. Which of the following is the correct decision?
answer choices
1. verify the results using the internal rate of return
2. either decision, accept or reject, would be correct
3. use the project cost of capital and reject the project
4. average the two costs of capital and reevaluate the project
use the company cost of capital and accept the project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
