Question: Suppose you are trying to evaluate a project with the following cash flows: Year Cash flow 0 -$25,400 1 $12,600 2 $8,600 3 $9,600 If
Suppose you are trying to evaluate a project with the following cash flows:
| Year | Cash flow |
| 0 | -$25,400 |
| 1 | $12,600 |
| 2 | $8,600 |
| 3 | $9,600 |
If the required return for the project is 7%, what is the net present value of the project?
Group of answer choices
$7,123.73
$1,723.73
$2,854.57
$10,320.24
$5,643.90