Question: Suppose you have a computer that has a 4 - stage pipeline and you have a workload that has an input set of operand values

Suppose you have a computer that has a 4-stage pipeline and you have a workload that has
an input set of operand values of size 8. If each *stage* takes one unit of time and that passing
results from one stage to the next is instantaneous, what is the average speedup in your
computer for this workload as compared to a computer with 1-stage functional unit? This single
functional unit takes 2 units of time to compute.