Question: Suppose you have been given responsibility for developing the six-month aggregate production plan at Soda Galore, a manufacturer of soft drinks. Your company makes three

Suppose you have been given responsibility for developing the six-month aggregate production plan at Soda Galore, a manufacturer of soft drinks. Your company makes three types of soft drinks: regular, diet, and super-caffeinated. Fortunately, all three types are made using the same production process, and the costs related to switching between the three types are so minimal that they can be ignored. Thus, you can treat your problem as an aggregate planning exercise where the planning unit is cases of soft drinks, regardless of what types of drinks they are.


The S&OP team has developed a forecast of demand for the first six months of the year as shown in Table 13-3. The S&OP team has also provided you with the cost data shown in Table 13-4.

The material cost of a case of soda is the same regardless of whether it is produced in regular time or overtime.

TABLE 13-3 Monthly Demand at Soda Galore


MonthDemand Forecast
January24,000cases
February36,000cases
March32,000cases
April40,000cases
May24,000cases
June84,000cases
Total Demand240,000cases
Average Monthly Demand40,000cases



TABLE 13-4 Soda Galore Planning Data





Current workforce
8workers
Average monthly output per worker
4,000cases per month
Inventory holding cost$0.60per case per month
Regular wage rate$16per hour
Regular production hours/month/worker
240hours
Overtime wage rate$24.00per hour
Hiring cost$1,000per worker
Subcontracting cost$1.70per case
Firing/layoff cost$1,500per worker
Beginning inventory
7,000(all safety stock)



Assume that employees negotiate an increase in the regular production wage rate to $20 per hour and $30 per hour for overtime. Also assume that Soda Galore always plans to hold at least 7,000 cases of safety stock to meet unanticipated customer demand. Assume that hiring and layoff/firing, if necessary, occur at the beginning of the month.

a. Using the planning information and the newly negotiated wage rates, develop a six-month production plan based on level production. (Leave no cells blank - be certain to enter "0" wherever required.)




Level Production Plan
MonthDemandRegular ProductionOvertime or Subcontract ProductionEnding InventoryWorkers Required (4,000 cases/worker)HireFire layoff
Jan.24,00040,000023,0001020
Feb.36,00040,000027,0001000
March32,00040,000035,0001000
April40,00040,000035,0001000
May24,00040,000051,0001000
June84,00040,00007,0001000
Total240,000240,0000178,000
20



b. Determine the cost of the level production plan.



Total cost
???????????????????



c. Using the planning information and the newly negotiated wage rates, develop a six-month production plan based on chase production. For the Overtime or Subcontract Plan, use the lowest monthly demand value to compute the size of the fixed workforce. (Leave no cells blank - be certain to enter "0" wherever required.)




Chase Production Plan : Adjust Workforce Size
MonthDemandRegular ProductionOvertime or Subcontract ProductionEnding InventoryWorkers Required (4,000 cases/worker)HireFire layoff
Jan.24,00024,00007,000602
Feb.36,00036,00007,000930
March32,00032,00007,000801
April40,00040,00007,0001020
May24,00024,00007,000604
June84,00084,00007,00021150
Total240,000240,000042,000
207


Overtime or Subcontract
MonthDemandRegular ProductionOvertime or Subcontract ProductionEnding InventoryWorkers Required (4,000 cases/worker)HireFire layoff
Jan.24,00024,00007,000602
Feb.36,00024,00012,0007,000600
March32,00024,0008,0007,000600
April40,00024,00016,0007,000600
May24,00024,00007,000600
June84,00024,00060,0007,000600
Total240,000144,00096,00042,000
02




d. Determine the cost of the chase production plan.





Total cost if workforce size adjusted???????????????
Total cost if overtime production used???????????????
Total cost if subcontracting used???????????????



e. After much internal discussion, the company decides to maintain a permanent workforce of 8 production workers. Given the same planning information and this new requirement, develop a six-month production plan based on hybrid production.(Leave no cells blank - be certain to enter "0" wherever required.)



Hybrid Plan
MonthDemandRegular ProductionOvertime or Subcontract ProductionEnding InventoryWorkers Required (4,000 cases/worker)HireFire layoff
Jan.24,00032,000015,000800
Feb.36,00032,000011,000800
March32,00032,000011,000800
April40,00032,0004,0007,000800
May24,00032,000015,000800
June84,00032,00044,0007,000800
Total240,000192,00048,00066,000
00


f. Determine the cost of the hybrid production plan. Use the overtime cost.




Total cost?????????

Step by Step Solution

3.34 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Develop a sixmonth level production plan as shown below Note Beginning inve... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!