Question: Suppose you have end item A. The lot sizing method for the item is FOQ (20). The leadtime is 1 week, the available on-hand inventory
Suppose you have end item A. The lot sizing method for the item is FOQ (20). The leadtime is 1 week, the available on-hand inventory is 100 units, and the safety stock requirement is 20 units. Demand forecasts for each week and customer orders due in each week are given in the following table:
| Week | 1 | 2 | 3 | 4 |
| Demand forecasts | 30 | 30 | 30 | 40 |
| Customer orders | 28 | 32 | 16 | 5 |
| PAB | ||||
| MPS quantity | ||||
| MPS start |
(a) What is the projected requirement in week 1?
units
(b) What is the initial available balance?
units
(c) What is the projected available balance at the end of week 2?
units
(d) What should be MPS start in week 3?
units
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock