Question: Sve & Exit Submit Exercise 2-2 Apply Overhead Cost to Jobs [LO2-2] Check my work Luthan Company uses a plantwide predetermined overhead rate of $23.20
Sve & Exit Submit Exercise 2-2 Apply Overhead Cost to Jobs [LO2-2] Check my work Luthan Company uses a plantwide predetermined overhead rate of $23.20 per direct labor-hour. This predetermined rate was based on a cost formula that estimated $278,400 of total manufacturing overhead cost for an estimated activity level of 12,000 direct labor- hours. The company incurred actual total manufacturing overhead cost of $267,000 and 11,300 total direct labor-hours during the period Required: Determine the amount of manufacturing overhead cost that would have been applied to all jobs during the period. Manufacturing overhead applied es Score answer > 2 of 7