Question: Swifty Inc. has two projects as follows: Initial CF CF1 CF2 CF4 Project . 830 -2,430 -2,980 1,180 1,480 CF3 1,000 1,000 1,880 3,880 B

Swifty Inc. has two projects as follows: Initial CF CF1 CF2 CF4 Project . 830 -2,430 -2,980 1,180 1,480 CF3 1,000 1,000 1,880 3,880 B 730 If Swifty set 2.46 years as a cut-off period for screening projects, which projects will be selected, using the payback period method? (Round answers to 2 decimal places, e.g. 125.25.) Project A payback period years Project B payback period years A will be selected