SWY has entered into a three-year contract worth RM500 million to construct a two-way bridge, aiming to
Fantastic news! We've Found the answer you've been seeking!
Question:
SWY has entered into a three-year contract worth RM500 million to construct a two-way bridge, aiming to alleviate traffic congestion. The construction costs incurred during each year are as follows:
- Year 1: RM90 million
- Year 2: RM130 million
- Year 3: RM210 million
What would be the profit or loss, if any, recognized for each financial year from Year 1 to Year 3?