Question: Syed is using probability distribution to determine the time to use for a particular activity on his project. He estimates that if he puts

Syed is using probability distribution to determine the time to use for 

Syed is using probability distribution to determine the time to use for a particular activity on his project. He estimates that if he puts his best workers on the task that they will finish in 8 days. If he put his least experienced workers on the task they will finish in 20 days but if he has a mix of worker most likely they will be done in 11 days. What level of (sigma) should he use to estimate that the task will take between 8 and 16 days?