Question: System Development Method b) You have been given a project to manage that has a reasonably well-defined set of requirements but has a very short
System Development Method
b) You have been given a project to manage that has a reasonably well-defined set of requirements but has a very short timescale. You are using the RUP to develop the project with short iterations. You have a small team working on it (fewer than 10 people), and unfortunately, less than a third of the way through the project, you lose an important team member due to long-term illness. Discuss the ways you might use to cope with this, and the different ways your coping strategies might impact cost, timescale, functionality etc. (10 marks)