Question: Table 1 below provide the information on cost - duration trade - off for Project Solaria. The indirect costs for each project duration are RM
Table below provide the information on costduration tradeoff for Project
Solaria. The indirect costs for each project duration are RM time units RM time units RM time units RM time units, and RM time units Report the total direct, indirect, and project costs for each duration. Identify the optimum costtime schedule for the project and the associated cost.