Question: Table 1 . Parameter Quantity Ore demand 1 0 , 0 0 0 tonnes / shift Stripping requirement 4 0 , 0 0 0 m

Table 1.
Parameter
Quantity
Ore demand
10,000 tonnes/shift
Stripping requirement
40,000 m3/ shift
Shovel loading time
4 minutes
Backhoe loading time
3 minutes
Average velocity of loaded truck
10 m/s
Average velocity of empty truck
15 m/s
Distance to and from waste disposal site
2500 m and 2800 m respectively
Haulage distance to stockpile
6.5km
Truck Capacity
50 m3
Truck discharge time
18 seconds
Truck waiting time
20 seconds.
Equipment utilisation
80%
Density of ore
2.200 tonnes / m3
Truck delay time
30 secs
Work Schedule
Two 8 hours shifts/day, six(6) days per week
what is the stripping ratio and recovery %?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!