Question: Table 1 shows activities and durations required to complete a specific project. Activity A Table 1 Predecessor Duration H B A I C A

Table 1 shows activities and durations required to complete a specific project. Activity A Table 1 Predecessor Duration H B A I C A J B K E B, D L F C, E M G F N a. Use information from Table 1 to create a Critical Path Method (CPM) Network. Use duration numbers for H, I, J, K, L, M and N as per your seven numbers of your matric numbers where H is the first digit, I is the second digit and so on until the last digit for N. If any of your matric number is zero, please change it to 1. b. Determine the critical path for the network. c. Generate Gantt Chart for the project using the network
Step by Step Solution
There are 3 Steps involved in it
To create a Critical Path Method CPM Network we first need to define the activities their predecesso... View full answer