Question: Table 1 shows the earned value analysis project case studies. Based on FIVE cases highlighted in Table 1, comment the status of each project cases
Table 1 shows the earned value analysis project case studies.
Based on FIVE cases highlighted in Table 1, comment the status of each project cases using the information given.
Table 1
| Project case | Planned Earned Value (BCWS)
| Actuals (ACWP) | Actual Earned Value (BCWP) |
| 1 | 800 | 800 | 800 |
| 2 | 800 | 600 | 400 |
| 3 | 800 | 400 | 600 |
| 4 | 800 | 600 | 600 |
| 5 | 800 | 800 | 600 |