Question:
Table 1 shows the time schedule for a project at Kings University College.
TASKS | PRECEDENCE | TIME |
1 | - | 16DAYS |
2 | 1 | 12DAYS |
3 | - | 8DAYS |
4 | 3 | 18DAYS |
5 | 1 | 22DAYS |
6 | 2 | 6DAYS |
7 | 4,5,6 | 2DAYS |
Required:
(i))Use table to construct an Activity-On-Node (AON) network diagram that depicts the major project activities and their sequential relationships.
(ii) Using the AON network diagram in (i) above, determine:
1. the length of each path.
2. the critical path.
3. the expected length of the project.
4. amount of slack time for each path.