Question: Table 11-3 Activity Immediate Predecessor Optimistic Pessimistic Variance A B 4 12 2 Most Likely 5 16 8 5 7 6 18 14 Standard Deviation

Table 11-3 Activity Immediate Predecessor

Table 11-3 Activity Immediate Predecessor Optimistic Pessimistic Variance A B 4 12 2 Most Likely 5 16 8 5 7 6 18 14 Standard Deviation 0.333 1.000 2.000 0.000 0.333 A D 0.111 1.000 4.000 0.000 0.111 A B, C 5 6 5 8 E According to Table 11-3, there are five activities in a PERT project. Which activities are on the critical path? A-B-C-D A-C-E B-D A-B-C-D-E B-E