Question: Table 2. Previous Project Activity Description Activity Time Estimates (Weeks) Immediate Predecessors Optimistic Most Likely Pessimistic Requirements A 2 3 4 Market Assessment B 4

Table 2. Previous Project

Activity Description

Activity

Time Estimates (Weeks)

Immediate Predecessors

Optimistic

Most Likely

Pessimistic

Requirements

A

2

3

4

Market Assessment

B

4

7

10

A

Design

C

5

6

9

A

Development

D

6

7

16

C

Testing

E

7

9

10

D

Revising

F

4

5

6

B, E

Documentation

G

3

6

10

D

Quality

Assurance

H

2

4

7

C, E

Pricing

I

2

2

2

B

Installation

J

3

4

14

F, G, H, I

Project Handoff

K

2

3

4

J

Table 3. Crashing Data

Activity Designation

Crash Time

(Weeks)

Normal Cost ($)

Crash Cost ($)

A

3

10,000

10,000

B

6

20,000

25,000

C

5

15,000

30,000

D

6

45,000

65,000

E

8

10,000

20,000

F

4

15,000

18,000

G

4

20,000

30,000

H

3

10,000

15,000

I

2

5,000

5,000

J

5

40,000

50,000

K

2

15,000

25,000

Questions

1. Crash the project by three weeks. (Excel may prove useful for this question)

2. What is the duration of the project prior to crashing?

3. Which activities did you crash?

4. What is the additional cost to crash the project by three weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!