Question: Table 2 : Project Crash Data Note: If multiple critical paths exist, select the path with the highest variance ( standard deviation ) to use
Table : Project Crash Data
Note: If multiple critical paths exist, select the path with the highest variance standard
deviation to use in probability calculations so that uncertainty is better accounted for.
Assignment Questions:
The critical path is ACDGKL
marks Suppose that the cost of being late to the market is estimated to be
$ per week if the project completion time exceeds weeks. Determine the
most "CostEffective" project completion time.
a Which tasks would you recommend crashing and how to achieve this
cheapest completion time and why?
b What is the total cost of crashing the project to complete the project in
weeks and is it worth it and why?
c What is the probability of completing the project in weeks with this
project plan?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock