Question: Table 2: Standard time for each element of assembly task in standard minutes (SM) Element No. Element of Task Time in standard minutes (SM) Press

Table 2: Standard time for each element of assembly task in standard minutes

(SM)

Element No.

Element of Task

Time in standard minutes (SM)

Press operations

1

Assemble poke subassembly (LH poke, RH poke, poke bush)

0.12

2

Fit poke subassembly to frog (poke S/A, poke pin, frog)

0.10

3

Rivet adjusting lever to frog (adjusting lever, rivet, frog)

0.15

4

Press adjusting nut screw to frog (frog, adjusting nut screw)

0.08

Total Time

0.45

Bench operations

5

Fit adjusting nut to frog

0.15

6

Fit frog screw to frog

0.05

7

Fit knob to base

0.15

8

Fit handle (Tote) to base

0.17

9

Fit frog subassembly to base

0.15

10

Assemble blade subassembly

0.08

11

Assemble blade subassembly, clamp and label to base and adjust

0.20

12

Make up box and wrap plane, pack and stock

?

Total Time

?

There are 12 elements in the process and standard times for each element of assembly task in standard minutes (SM). However, element 12 is in the process of time and motion study where the results are on Table 3, where the operations analyst rated worker at 85% where worker performed 85% of the normal time and the firm uses allowance factor is 15%. (Used this formula for Standard Time= Normal Time/ (1-Allowance Factor)

1. Here, you must compute the required takt time, cycle time/process times, throughput time, total work time, normal time, standard time, showing how line is balance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!