Question: Table 2.1 below consists of data collected for a project: Act Predecessor Optimistic Most likely Pessimistic a - 3 6 8 b - 2 4
Table 2.1 below consists of data collected for a project: Act Predecessor Optimistic Most likely Pessimistic a - 3 6 8 b - 2 4 4 c - 1 2 3 d a,b 6 7 8 e c 2 4 6 f e 6 10 14 g e 1 2 4 h d 3 6 9 i g,h 10 11 12 j f,g 14 16 20 3
2.1 Using PERT, calculate the time (t) for each activity. (10)
2.2 Draw the network diagram (AON) based on the above and identify the critical path.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
