Question: table [ [ , , , , , ] , [ , Y , TaskA, 1 day,Wed 1 4 Wed 1 4 , ]

\table[[,,,,,],[,Y,TaskA,1day,Wed 14 Wed 14,],[,7,Task B,2 days,Fri 160 Mon 19,],[,+,TaskC,2 days,Tue 20/Wed 21,],[,,,TaskD,-1 day,Tue 20/ Tue 20/,],[,+,TaskE,1 day,Thu 222? Thu 221,],[,+,Taskf,0.5day,Thu 22? Thu 221,],[,t,TaskG,1 day,Mon 19 Mon 19,],[,1,TaskH,1day,Fri 160Mon19,]]
a) Start-to-finish dependency:
b) Finish-to-start dependency:
c) Finish to-finish dependency:
d) Start-to-start dependency:
2.2) Based on the diagram shown below, answer the questions:
a) What is the total duration of the project? (2 marks)
b) What is the critical path of the project? (3 marks)
c) How many days can activity A be delayed without delaying any following activities? (2 marks)
d) What is the total float on activity D?(2 marks)
 \table[[,,,,,],[,Y,TaskA,1day,Wed 14 Wed 14,],[,7,Task B,2 days,Fri 160 Mon 19,],[,+,TaskC,2 days,Tue 20/Wed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!