In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
A Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project
B Make sure proper testing gets completed to minimize the risk highlighted
C Add this risk to the lessons learned register on project completion
D Add the stakeholder to the stakeholder register and add the risk to the risk register