Question: Table 3 Project A Project B Time 0 8,000 4,000 Time 1 9,000 3,500 Time 2 1,000 6,000 Time 3 1,000 9,000 QUESTION 7 Consider

Table 3 Project A Project B Time 0 8,000 4,000 Time 1 9,000 3,500 Time 2 1,000 6,000 Time 3 1,000 9,000 QUESTION 7 "Consider the cash flow of the two projects depicted in Table 3. If WiseGuy Inc. uses IRR rule to choose projects, which of the projects (Project A or Project B) will rank highest? ---" Project A. Project B. Project A and Project B have the same ranking. Cannot calculate a payback period without a discount rate